Schedule

Work to be completed in stages through 2009

Prep Stage
Tasks:
 Remove & Reconstruct Median
Traffic Impacts: Shift traffic to outside edges of Route 1
Estimated Timeframe: December 2006 to February 2007

Major Construction Stages

  Stage 1  Stage 2 Stage 3 Final Stage 
Work Focus Reconstruct south side Reconstruct north side Reconstruct median area Cleanup, bridge painting and landscaping
Traffic Impacts Shift all traffic to the north side of Route 1 Shift all traffic to the south side of Route 1 Shift traffic to outside edges of Route 1 Minimal
Estimated Timeframe February 2007 to March 2008 March 2008 to January 2009 February 2009 to September 2009 October 2009 to the end of December 2009

 